The Environment Agency was set up in 1996 covering England and Wales but in 2013 became an England-only non-departmental public body of the Department for Environment, Food and Rural Affairs.

Nuclear responsibilities

Nuclear spin.png This article is part of the Nuclear Spin project of Spinwatch.
Onr-ea.jpg

The Environment Agency is 'responsible for regulating the nuclear industry on environmental matters such as disposals and discharges of radioactive waste from the site, discharges of cooling water and operation of standby generators'.

Our position on nuclear power is that we:

  • recognise nuclear power's role in providing low-carbon electricity generation as part of the national energy mix
  • insist that nuclear installations achieve high standards of safety, security, environmental protection and radioactive waste management
  • believe that Government and the Nuclear Decommissioning Authority should continue to demonstrate credible commitment to making progress with geological disposal of radioactive waste.

Waste

Since 6 April 2010 has regulated the disposal of radioactive waste from nuclear sites under the Environmental Permitting (England and Wales) Regulations 2010 (EPR). We also regulate certain aspects of the keeping and use of radioactive sources on nuclear sites. These Regulations replace the Radioactive Substances Act 1963 (RSA93). For convenience we call this Radioactive Substances Regulation (RSR).

Generic Design Assessment

The UK's two civil nuclear regulators – the HSE and Environment Agency – have been carrying out a new process called 'Generic Design Assessment' (GDA), which looks at the safety, security and environmental implications of new reactor designs before an application is made to build that design at a particular site. [1] In March 2008, the initial assessment of four nuclear power station designs was completed. No shortfalls in any of the four designs were found. A series of reports on each design were published. [2]

The next stage was going to be a prioritisation process to select a maximum of three reactor designs to proceed to the next stage of the assessment, but Atomic Energy of Canada Ltd announced in April 2008 that it was pulling its ACR-1000 design out of the process to focus on its home market. [3]

On 12 June 2008, HSE and the Environment Agency announced that they were starting the next, more detailed stage of the GDA process - referred to by HSE as Step 3 - for the remaining three designs.

Then in September 2008 General Electric's nuclear venture with Hitachi Ltd. asked the HSE to temporarily halt the process of assessing its so-called Economic Simplified Boiling Water Reactor so that it could focus its efforts on getting U.S. approval instead. [4]

This left only the Toshiba-Westinghouse AP1000 design and the Areva-Siemens European Pressurised Water Reactor (EPR) in the assessment process.

At the end of the process the regulators will make statements setting out their conclusions about the acceptability of the designs.

Updates from the HSE on the process are on its GDA Reports webpage.

People

Contact

Website:

Resources

Notes

  1. See UK Nuclear Regulators: Nuclear Reactor Assessment HSE website accessed December 2008.
  2. Generic Design Assessment Reports, HSE website, accessed December 2008.
  3. T.Hamilton,'AECL abandons effort to sell UK reactors' Toronto Star, 5 April 2008.
  4. L.Paulsson, 'GE asks UK to suspend approval of nuclear reactor' Bloomberg, 17 September 2008.